Planning fallacy
In short
The planning fallacy is the tendency to believe that your own project will go according to plan, even when you know that most similar projects ran late. The term was proposed by Daniel Kahneman and Amos Tversky (1979). The big examples are well known: the Sydney Opera House was supposed to be finished in 1963 for 7 million dollars, and it opened in 1973, in a scaled-down version, for 102 million. But the effect also shows up on a small scale: in assignments, renovations, a report to finish.
What it says
The core study. Buehler, Griffin and Ross (1994) asked 37 final-year students who were close to finishing their honors thesis when they thought they would hand it in. They asked for three estimates: the most realistic one, one for the case where everything goes perfectly, and one for the case where everything goes badly. They then recorded when each thesis was actually submitted.
On average, the students estimated 33.9 days, and the thesis took them 55.5. Only 29.7% finished by their estimated date. What’s more, even the pessimistic case wasn’t pessimistic enough: only 48.7% finished by the date they had given for the case where “everything went as poorly as it possibly could”. The estimates were not worthless, though: those who estimated longer really did take longer. The error was a shift of everyone toward optimism.
The same pattern appeared in the article’s other studies, with school assignments and household tasks. For example, students who had a deadline for an assignment estimated on average that they would finish in 5.9 days, and reported finishing in 11.0. Participants said they were 70–84% sure of their estimates.
Why it happens. When the authors asked participants to think aloud while estimating, they found that almost all their thoughts were about the future plan: how they would work, what they would do first. Only 7% of thoughts were about past experiences, and very few were about possible obstacles. When they thought about past delays, participants explained them by causes that were transient and specific to that situation.
Kahneman and Lovallo (1993) call this the inside view: you treat the project as a unique case, build scenarios about how it will go, and ignore the statistics of similar projects. The outside view, as Flyvbjerg (2006) describes it following Kahneman, works the other way round: how long did projects like this usually take?
What worked. In the fourth study of Buehler et al. (1994), simply remembering how long previous assignments had taken changed nothing. Estimates became realistic only when participants were asked to explicitly connect their past experiences to the current assignment: to imagine how their usual pattern might repeat itself. The share who finished on time rose from 29% to 60%.
In large projects. Flyvbjerg (2006) describes applying the outside view to project management, under the name reference class forecasting, in three steps:
- choose a class of similar past projects, broad enough to be statistically meaningful and narrow enough to be comparable;
- establish how outcomes were distributed in that class, for example cost or time overruns;
- place your project within that distribution, instead of estimating it from the plan.
The method was used in the UK for the costs of transport projects. Flyvbjerg describes the application, but the article is not an experiment that measures its effect.
Example
Flyvbjerg (2006) relates a story told by Kahneman. A team writing a new school curriculum estimated, each member separately, between 18 and 30 months to finish. Then one of them, an expert in such curricula, was asked how long similar teams had taken. The answer: about 40% had given up, and the rest had finished in 7 to 10 years. The team carried on anyway. It finished after eight years, and the curriculum was rarely used.
How to apply it
The steps below are a practical approach we propose, based on the studies cited.
- Start from similar cases, not from the plan. First ask how long your last projects of this kind took you, or how long they took others. Only then adjust for what is different now.
- Explicitly connect the past to the current project. In Buehler et al. (1994), remembering alone didn’t help. What helped was picturing concretely how the usual delays could repeat in the current project.
- Don’t rely on the pessimistic case. Even the “if everything goes badly” estimate wasn’t long enough for half of the students.
- Keep a record. Write down your estimates and the actual durations. Roy et al. (2005) show that people also remember past durations as shorter than they were, so memory alone is not a reliable base.
- Let someone else estimate. In Buehler et al. (1994), observers estimating for someone else gave longer timelines. Careful, though: they erred in the opposite direction, so they weren’t more accurate either.
Limits and nuances
- Not everyone always underestimates. Halkjelsvik and Jørgensen (2012) reviewed studies of time predictions. Underestimation appears more often than overestimation in studies from engineering and management, but not in those from psychology. The result depends on the type of task and on how the question is asked.
- Another explanation: memory. Roy et al. (2005) propose a complementary explanation: people base their estimates on how long they think past tasks took, and those memories are themselves too short.
- Less bias doesn’t mean more accuracy. In Buehler et al. (1994), neither the pessimistic estimates, nor the observers’ estimates, nor those from the condition that removed the bias were more accurate on average. They only erred differently: less optimistically or, for the observers, in the opposite direction.
- Large projects have other causes too. In public projects, overruns can also come from estimates made optimistic on purpose, so that the project gets approved. Flyvbjerg (2006) calls this strategic misrepresentation and treats it separately from the error of judgement.
- Limited participants. The 1994 studies used psychology students and academic or everyday tasks lasting days or weeks.
Sources
- Daniel Kahneman, Amos Tversky (1979). Intuitive prediction: Biases and corrective procedures
- Roger Buehler, Dale Griffin, Michael Ross (1994). Exploring the "planning fallacy": Why people underestimate their task completion times
- Daniel Kahneman, Dan Lovallo (1993). Timid choices and bold forecasts: A cognitive perspective on risk taking
- Bent Flyvbjerg (2006). From Nobel Prize to project management: Getting risks right
- Michael M. Roy, Nicholas J. S. Christenfeld, Craig R. M. McKenzie (2005). Underestimating the duration of future events: Memory incorrectly used or memory bias?
- Torleif Halkjelsvik, Magne Jørgensen (2012). From origami to software development: A review of studies on judgment-based predictions of performance time
See also: Circle of competence, Implementation intentions